Project Information Sheet
Hakone Gardens Trail,
Saratoga, CA
1992
- PROJECT LOCATION
- : Hakone Gardens, Hwy 9, Saratoga
PROJECT DESCRIPTION: New trail,
approx. 1,500 lineal feet from Hwy 9 near the
entrance gate to the gateway of Hakone
gardens.
CONTRACTING AGENCY: Hakone
Foundation, Saratoga.
ESTIMATED FINISH DATE: Aug. 29,
1992
NUMBER OF WORKDAYS: 6 (remaining
workdays scheduled: 4/16/92 (rain date 4/23), 5/30
(r.d. 6/6), 6/27)
PROJECT SPECIFICATIONS:
a) TREAD WIDTH: 36 inch with even
tread. One short (20- 30 ft) section may be 30
inches wide.
b) GRADE: Maximum 10%
c) DRAINAGE: Standard drain dips
and one culvert
d) FINISH: Side cuts and banks
finished to natural contour and slope
HAZARDS: Poison oak
RESTROOMS: At parking lot off
entrance drive
EMERGENCY INFORMATION
NEAREST PHONE: At parking lot (near
restrooms)
FOR EMERGENCY DIAL 911
NEAREST HOSPITAL: Community
Hospital and Rehabilitation Center of Los
Gatos-Saratoga
815 Pollard Rd.
Los Gatos
(408) 378-6131